Building a house that complies with the energy code can involve a lot of trade-offs. And if youâre aiming for above-code performance, where the stakes are higher, the trade-offs become even more challenging to evaluate. High-performance builders are pioneers, and each high-performance house is an exploration of uncharted territory.
One such project is a net-zero home in Bangor, Maine, that was designed and built by civil engineer Mark Dwyer and custom builder and remodeler David Kelly. While Dwyer has experience in spec remodeling, this house was a side project for him; in his day job, heâs a research engineer with the Advanced Structures and Composites Center at the University of Maine in Orono. For builder and remodeler David Kelly, of Bangor-based House Revivers, the collaboration with Dwyer offered a chance to deepen his expertise in high-performance home building.
High-performance houses in Maine tend to emphasize superinsulation, but for this project, Dwyer and Kelly settled on a different approach. Although the 1,400-square-foot house is extremely airtight, its insulation levels are only moderately above the code-required baseline. Advanced mechanicalsâan air-to-water heat pump supplying a radiant slab, with site energy provided by a rooftop solar arrayâpush the homeâs efficiency to the net zero goal.
The home is one level, with a monopitch truss roof (the main house roof slopes from a high south wall toward the north, while the roof of the 700-square-foot garage, topped by solar panels, slopes from north to south). Large windows on the tall south wall let in daylight and provide solar heating of the living room and kitchen; bedrooms and closets are located on the north side.
Throughout the process, the duo fine-tuned the balance between envelope characteristics and mechanical systems, aiming to optimize whole-house performance. They had the opportunity to try out a few unusual methods along the way.

The slab detail was familiar to trade contractors.
The Home’s Foundation
Bedrock at the homeâs location lies 1 foot to 3 feet below grade. To minimize digging and reduce foundation costs, Kelly and Dwyer chose a frost-protected slab on grade, with 4 inches of R-5 extruded polystyrene (XPS) under the slab and 2 inches at the edge.
âAt this point, Iâve done four different flavors of frost-protected slab,â says Kelly. Some of his previous designs have included as much as 8 or 10 inches of sub-slab and slab-edge insulation. âThis one isnât the best example from an energy-performance standpoint,â he says. âWe have R-20 under the slab and R-35 in the wall assembly, but then that one little area at the slab edge is only R-10. Thatâs the weak spot. But as with all the details weâve chosen, there is a cost trade-off.â

Tim Healey
The foundation-to-wall juncture was a relative weak spot in the building envelope. The slab-edge insulation is thin compared with other parts of the building, and while the lowcost slab forming approach was familiar for the sitework and concrete contractors, the air-sealing detail where the wall met the slab turned out to be trickier than planned.
On the other hand, the method chosen for this house has practical advantages. âThe nice thing about this slab method,â says Kelly, âis that you can show it to any earthwork or foundation contractor anywhere, and they will know exactly what you are talking about. You haunch the gravel, you put your radon system in and pack gravel around it, and you have a nice base to put your XPS on.â
One downside is that the labor of haunching the gravel and piecing in the XPS takes time, notes Kelly. In researching slab insulation, Dwyer says, he found wide agreement that R-10 (2 inches of XPS) would be sufficient. Even so, adding a second 2-inch layer, for R-20, seemed cheap enough to be cost-effective. The second layer also allowed Kelly and Dwyer to try something new: They routed channels for the domestic water lines into the lower layer of foam and embedded all the tubing in the grooves. âIt took maybe eight or 10 man-hours to rout the grooves and push all the pipes in,â says Dwyer, âand we saved maybe $400 in pipe insulation.â

The radiant-slab tubing was time-consuming.

The conventional slab edge detail received an economical stucco finish.
Running hydronic tubing above the XPS for the five-zone radiant slab system was a more significant labor cost. A mini-split setup would have been far less expensive, Kelly notes, and would have allowed easy access for maintenance or repair, but the hydronic system is extremely efficient and offers the comfort of a warm slab during Maineâs frigid winter months.
To finish the vertical slab-edge foam, Kelly and Dwyer chose a common low-cost detail: acrylic stucco troweled over the foam.
Walls and Windows
Throughout the project, Kelly and Dwyer worked to balance the homeâs energy goals against the cost and buildability of the assemblies.
âDavid has built three net-zero houses using various wall details,â says Dwyer. âWe considered all of those possibilities for this house, starting with Larsen trusses with dense-pack cellulose. But David came up with a turnkey price for that 20-inch-thick Larsen-truss wall, and it was very high. Just the dense-pack was about $18,000. So we decided that wasnât affordable.â Another option was a double 2×4 stud wall. But that would also be costly to frame and insulate, and it would require complicated finish details at the deep window openings.
In the end, the team came back around to a basic 2×6 frame with 2 inches of XPS on the outside. The exterior foam would cut down on thermal bridging through the wall framing, and insulating the wall cavities with Roxul mineral wool from the inside would be quick and easy.

Concrete âcookiesâ used to brace the wall framing were only partially effective.
Bracing the walls during framingâespecially the tall front wallâwas a challenge. The site soil was too shallow for stakes to bite, and the framing crew didnât want to risk penetrating the hydronic tubing by spiking blocks for braces into the slab. Instead, they set precast concrete âcookiesâ on the slab and spiked the braces into those. Dwyer admits that method didnât work wellâthe concrete-to-concrete contact surface was too slippery, and some of the walls ended up out of plumb by more than a 1/2 inch. âNext time,â he says, âIâd try my luck with the stakes in the dirt.â

Kelly taped the sheathing joints at the openings.

Then he screwed on window bucks.
To frame out the window openings, the team first applied a 3M 8067 tape air seal to the corners of the rough openings, then fastened on bucks made from 2×6 lumber ripped to a little over 4 inches. This depth would accommodate a wall pack-out consisting of 2-inch XPS foam, 3/4-inch rainscreen strapping, and 5/16-inch fiber-cement siding; the bucks would project out another inch as a backing for metal trim. After applying the bucks, carpenters cut the foam to fit tight to them, taped the foam to the bucks, and applied strapping over the foam.
âThe bucks worked out well,â says Kelly, noting that this method requires careful attention at the rough-framing stage. âI would do it again. Also, you could accommodate a fatter wall that way if you were to use thicker insulation on the outside.â
Rainscreen Cladding
For the homeâs cladding and window trim, Kelly and Dwyer borrowed a detail from commercial constructionâthey used metal trim for the windows and applied 4×8 panels of fiber-cement HardiePanel siding, cut tight to the windows and installed over 1×4 furring. This system isnât common on homes, but for a small house in a modern style, it can provide a clean, simple look.

Roofers installed metal window trim.

Kelly caulked the window joints.
Over the window bucks, they used vinyl-coated steel coil stock, custom-bent on-site and applied by the crew that installed the homeâs white standing-seam metal roof. The same roofing company also installed the homeâs fascia using the same heavy-gauge material, so the window and door trim matches the roof and the eaves. (Soffits are pearl gray HardiePanel.)
Kelly used a commercial caulkerâs âsausage gunâ to apply white Tremco caulking to the joints between the white window frames and the white metal trim, tooling the caulk carefully for a clean, sharp finish.
Behind the joint locations between cement panels in the field, carpenters applied a detail made with lighter aluminum coil stock to the wall, before installing the panels. Gapped about 3/8 inch, the blue panels stand proud of the recessed white trim, creating a sharp shadow line.
The unfamiliar cladding system proved troublesome for the carpentry subs on-site. Many of the panels were about 1/8-inch out of square, which caused problems with the careful layout and cuts required to fit the panels to the windows. Production was slow at first, says Dwyer: âI was paying them to learn.â In the end, Dwyer ran most of siding himself with a hired helper.
The Roof System
In a one-story house, the roof represents a relatively large surface area. âYour best building for net zero is a cube,â Dwyer notes. âThat maximizes your volume and minimizes your surface. And the other net zero houses that David has done were more compact boxes. But this house is all on one level, so weâre throwing that out the window. This is a big roof.â
Accordingly, super-insulating the roof while limiting its cost was an important challenge. âFirst we looked at wood I-joists,â says Dwyer, âbut they had to be 16 inches on-center, and they cost $3 to $5 a lineal foot. So that quickly became too expensive.â
Trusses at 16 inches on-center also werenât cheap, says Dwyer. However, changing the trusses from 24 inches deep to 32 inches deep, it turned out, allowed 2-foot-on-center spacing. âThat dropped out 15 trusses,â says Dwyer, âand the price went down $4,000.â
Although it was unusual, Dwyer says, the roof construction process was one of the few steps that went exactly as planned. Trusses went on quickly, and applying the OSB air barrier to the underside of the trusses was straightforward.

Installing the OSB air barrier

Insulating from above
With the ceiling OSB in place, the crew from Penobscot Home Performance could efficiently blow in the cellulose from above, while carpenters worked behind the insulators and decked the roof.
The deep trusses allowed room for ample R-value in the roof system. âOriginally, we were going to insulate the roof with 14 inches of Roxul, shooting for about R-60,â says Dwyer. âBut once the truss depth got bumped up, we said, âLetâs just blow in 24 inches of open blow cellulose. That gives us R-84 and it leaves a 6-inch gap at the top for ventilation.â We got a price of $3,500 for the insulation, installedâversus $6,000 plus labor for a lower R-value worth of Roxul.â
Critical Junctures
From foundation to roof, Dwyer and Kelly chose construction methods and insulation levels that balanced performance against cost and buildability.
The 4 inches of insulation beneath the slab and the 2 inches at the slab edge arenât much of a departure from code, and the construction method didnât pose much of a challenge to the trades on-site. The wall system the pair chose isnât far above code either, and the methodâexterior foam applied over a sheathed stud wallâis becoming commonplace in much of the country. The roof systemâloose-blown cellulose in a trussâwas also conventional, even if the construction process was a little out of the ordinary.
In a high-performance house, however, itâs not just the main assemblies that matterâitâs also the transitions from one assembly to the next. And at the major junctures in the houseâthe foundation-to-wall joint, and the wall-to-roof jointâKelly and Dwyer faced a few challenges.
âThe big issue with our slab edge,â Kelly points out, âisnât so much the insulation level, but the air leakage that you typically get between the bottom plate and the slab. The transition between the foundation and the wall can often be a weak juncture.â For this house, the original plan for air-sealing that joint had been to continue the sub-slab poly vapor barrier up onto the ZipSystem wall sheathing, and tape the plastic to the wall.
That detail turned out to be impractical to construct, however. Kellyâs original idea for the slab pour had been to set the XPS slab edge foam against the wood foundation forms, chalk a line, cut the foam off at the line, and use the edge of the foam as a guide for leveling the slab. âBut our foundation contractor advised us that the foam was going to be so loosey-goosey that there would be no way to keep it dead level where we wanted it,â says Kelly. Instead, the concrete crew ran both the wooden forms and the insulation higher than the slab elevation, then set a string line to guide striking and screeding the wet concrete.
âIn the future,â Kelly says, âI donât care what the extra cost isâIâm going with the L-shaped foam forms at the foundation edge. Because errors at this stage, either in square or in level, compound one another as you move forward. So even if you spend more money on that L-shaped form, youâre still saving, because it makes everything else a little bit easier.â
The intersection between the wall and the roof system offered a similar puzzle. There, Kelly and Dwyer maintained a continuous air barrier by draping poly over the top plate before setting the trusses, and taping the poly to the OSB applied to the underside of the trusses.
But connecting the lower edge of the poly to the wall was a challenge. For structural reasons, the sheathing on the walls had to extend up onto the heels of the monopitch roof trusses. So the poly at the wall joint had to be taped to the inside face of the sheathing, between the studs. Itâs not a perfect air seal, Kelly admits, because the poly isnât sealed to the sheathing behind the studs.
On the outside, the ZipSystem wall sheathing is sealed with Zip tape. Windows are sealed into their openings with both tape and caulk. And the ceiling under the roof trusses has only two penetrations (the vent stacks for the homeâs plumbing drains), because all the ventilation tubing and ceiling wiring runs in cavities created within the 2×4 build-down. Even with the challenges at the wall base and the wall top, Kelly says, he expects the homeâs airtightness to test out well below 1 ACH50.

Tim Healey
The roof-to-wall air-barrier transition was another tricky element. Poly overlapping the wall plate had to be taped to the inside face of the wallâs Zip sheathing by hand, one stud bay at a time. But the walls and roof were quick and easy to frame, and the loose-blown insulation in the deep truss roof went in quickly at the same time as roof sheathing was applied.
Site Energy and Mechanicals
Photovoltaics play a key role in the homeâs net zero strategy. âThe idea was to spend a little more on the heating system, spend less on the insulation, upsize the PV system so it covers the energy to run the heating system, and come out net zero in the wash,â says Dwyer.
Kelly learned how to install solar panels himself on previous projects, on the advice of his electrical contractor. With multiple PV installs under his belt, he has set up a side business as a PV contractor. Kelly says learning to put in solar panels yourself could be a good move for any custom builder. Anyone with good carpentry skills can easily master installing the brackets and panels, he says, and the simple plug-and-play inverter and wiring harness systems make the hookups easy after a little study. On this job, Kelly says, he delivered the solar array at cost for about $1.80 per watt; the going rate from specialty contractors is more like $2.50 per watt. An electrician oversees the job, installs and connects the breaker panel, and steps in whenever his skills are needed.

Kelly saved cost by installing the PV brackets and panels.
As for the loads, Dwyer designed the air-to-water heat pump hydronic radiant system for a peak winter heating load of 17,500 Btu/hr., based on a Manual J calculation. That Manual J estimate is probably high, given Kellyâs rigorous attention to airtightness details. Windows on the homeâs south face will bring in sunshine on cold days, satisfying some of the homeâs heating loads. And the systemâs five zones and two hydro-air fan coils (one in the living room and one in the master bedroom) mean that the system can be fine-tuned to match individual room needs throughout the year.
âItâs always hard with a new house to size a PV array,â Dwyer points out. âYou donât have years of electrical bills to document energy demand. David installed 5.2 kW on his other net zero houses, which also heat with heat pumps. So here we just went a little bigger. And it turned out that 24 panels fit on the garage roof perfectly, so it ended up at 8.5 kilowatts.â
With annual net metering, surplus summer power is sent into the grid; in winter, when production drops below daily demand, the utility credits the difference back to the customer. Any annual surplus is a gift to the power company. âWhat I always tell people about net zero,â says Kelly, âis that you want to come as close to it as you can without hitting it.â
What if the array produces too much? âThe utility will love us,â says Dwyer. Says Kelly: âMaybe theyâll put in a hot tub.â
Photos by Ted Cushman, David Kelly, and Mark Dwyer.