Clark Ellis, a Pipeline workshop⢠colleague of mine, recently published an article in Big Builder, titled âBudget Buster No. 1,â about the inattention paid to production capacity in the annual budgeting process. It is a worthwhile read. In it, Clark attributed The Pipeline: A Picture of Homebuilding Production, Second EditionŠ for the important explanation of calculated cycle time.
Here is the full picture, excerpted from the book itself, and covered in every Pipeline workshopâ˘.
The intrepid, results-based consultant walked to the front of the conference room, now filled with a cross-section of teammates and leaders responsible for production.
On the erasable board, she started a list:
Pipeline
âWe have a lot of work to doâ, she said. âThe clearest pictureâthe best visual imageâwe can convey of RB Buildersâ production system is that of a pipeline. That being the case, what is the purpose of this pipeline?
âWhat does it do? What does it carry, and what does it deliver?â
âI would say that the pipeline does two thingsâ, offered the VP of Construction. âIt carries our work-in-processâit carries houses under constructionâand it delivers closings â completed homes. Soâits purpose is to produce completed homes, and generate Revenue from the closings that ensue.â
The intrepid, results-based consultant added to her list.
- Pipeline
- Pipeline Size v. Pipeline Capacity
- Cycle Time
- Work-in-Process
- Throughput
âOkay. Then what is the capacity of the pipeline to do that? How many houses â how much work-in-process â can the pipe carry?â, she asked, âHow do houses get into the pipeline? And â how many closings is it supposed to produce?â
âAs many as we can put in it. However we want to put them in it. Whenever we want to put them inâ, one of the superintendents quipped. âOkay. Weâre told weâre supposed to generate an even and sufficient rate of sales, starts, and closings.
âThat part makes sense. We just canât seem to achieve it.
âAndâif we could smooth-out our rate of sales, starts, and closings â then we could probably also manage to maintain a consistent level of work-in-process in the system.
âThat part makes sense, too.
âButâas for the capacity of the pipeâapparently we think it has unlimited capacity, because every start we put in the pipeline will eventually be completed and closed. As for the outputâthe throughputâthatâs a budgeted number of completed houses that turn into closings every year, sometimes we make it, sometimes we donât.
âAs far as how houses actually get into the pipeline, there is a start matrix, which acts as the pipeâs control valve. Under the old production system, the start matrix prescribed both the order and rate of starts, and âpushedâ the starts into the system. Under the new production system, the start matrix only prescribes the order; houses are supposed to be âpulledâ into the system at the rate of closings.â
âOkayâ, said the intrepid, results-based consultant. âI have several questions. Firstâis there a difference between the size of the pipe and its capacity? Second, how many homes should you have under constructionâhow much WIP do you needâin order to reach your budgeted closings? Thirdâhow long is it supposed to take you to build a house, and how long does it actually take you?â
âYesâI suppose there is a difference between size and capacityâ, said the VP of Construction. âThe size of the pipeline would be defined by the amount of work-in-process, while the capacity of the pipeline would be a function of output in relation to size.
âThere is a limit to how much it can hold, soâyesâthe size of the pipe is finite.
âYesâthere is a connection between how much the pipe can hold and how much it can produce. We think the pipe should be able to hold 100 houses, and we think the pipeline should be able to produce 240 completed houses a yearâat least, thatâs the budget â which is 20 closings per month. So, you could say that the size of our pipeline is 100 houses, and its capacity is 20 completed houses per month.
âIn terms of our cycle time, it varies depending on the house plan, but our construction schedules call for an average of 120 daysâ, the VP of Construction continued. âWe know we are nowhere near that fast. Most of our homes finish late. I would say that eighty (80%) percent of our houses take between 160 and 200 days.â
âIf you close 240 homes with 100 houses in WIP, your cycle time is 150 daysâ, said the intrepid, results-based consultant, â30 days longer than the schedule. But, this year, you are only on track to close 200 homes, meaning your cycle time is pushing 180 days.â
âThen we agreeâ, replied the VP of Construction. âThe way we measure it, our cycle time has been averaging around 180 days. There is considerable variation, particularly on individual jobs; some take more time, some take less time. But, the overall average is around 180 days.â
The intrepid, results-based consultant moved to the erasable board at the front of the conference room, selected an erasable marker, and wrote:
CT = 120 days WIP = 80 houses T = 240 homes
CT = (WIP á T) x Days (80 á 240) x 360 = 120 days
WIP = (CT x T) á Days (120 x 240) á 360 = 80 houses under construction
T = (WIP á CT) x Days (80 á 120) x 360 = 240 closings
âThere is, in fact, a direct connectionâ, she said. âThere is an accepted, proven mathematical relationship between cycle time (CT), the level of work-in-process (WIP), and the throughput (T) of a process. Soâif you know two of the values, you can always calculate the third value.
âThere are two laws of production that deal with this relationship. The one I just mentioned, called Littleâs Law, and one which we call the Law of Variability Buffering, which tells us that every system will protect itself from unplanned variation and uncertainty with some combination of â you guessed it â longer cycle time, more inventory (work-in-process), or excess/unused capacity.
âRegarding the difference between calculated cycle time and measured cycle time, there are two ways to determine it. You have measured cycle time, which is the average, or mean duration, of a set of jobs; its value lies in examining the forensics of individual jobs, in order to eliminate the causes of problems, variation, and waste. Itâs where we use kaizen, PDCA.
âThe value of measuring average cycle time lies in the selection of individual jobs to examine, because they are outside the lines of statistical control.
âAnd, you have calculated cycle time, which is the relationship between completed jobs and work-in-process; the value of calculated cycle time is in providing a picture of the condition and performance of the entire system.
âIn terms of what is actionable, measured cycle time is actionable at the level of every future job based on the forensics of past jobs, while calculated cycle time is actionable in ways that affect the performance of the entire system.â